Watkins awards building contractsWATKINS GLEN—Three contracts for work on the municipal building were awarded at the village of Watkins Glen board of trustees regular meeting Tuesday, Jan. 18. The general contractor bid submitted by Welliver McGuire, Inc. of Montour Falls for the amount of $509,690 was accepted. HMI Mechanical Systems, Inc. from Lyons, N.Y. bid for the plumbing contract at $47,390 was also accepted. The electrical contract was awarded to John Mills Electric, Inc. from Elmira Heights for the bid of $152,100. The bid for the heating, ventilating and air conditioning was rejected on advice from the architect. A new bid process for this contract was submitted (after press time) Tuesday, Jan. 25. |